The Aqua Pilot project is intended to prepare for the partial automation of the electric ferry Sankta Maria II, between Wasserbillig in Luxembourg and Oberbillig in Rhineland-Palatinate. Its budget is funded by the European Union, Germany and Luxembourg. But the announcement still concerns preparatory work and future trials: it does not mean that automated crossings are already in service.
A ferry linking two municipalities on either side of the Moselle
The Sankta Maria II provides a link between Wasserbillig, in the Luxembourg municipality of Mertert, and Oberbillig, in Germany. For residents, cross-border workers and visitors, the ferry avoids a detour by road. According to Luxembourg’s Minister for Mobility, Yuriko Backes, around 160 000 passengers use it each year. This figure, provided by the authorities, gives an indication of the current use of this crossing.
The boat has been electric since 2017. Aqua Pilot concerns a different step: equipping the route so that certain navigation operations can be automated, under defined conditions and with human supervision. The project is cross-border, but responsibilities are shared between several German and Luxembourg partners, as well as through European funding.
A budget of close to two million euros
The Luxembourg government puts the total cost at around two million euros. The planned funding is split between 60 % from European funds and 40 % in German and Luxembourg co-funding. Luxembourg is contributing around 290 000 euros. The Land of Rhineland-Palatinate has also announced support of around 290 000 euros from its regional funds.
The report on the presentation published by Chronicle.lu gives a more precise amount of 1 960 900 euros and details the announced breakdown: 60 % through the Interreg Greater Region programme, 15 % for each of the two national ministries, and 5 % for each of the municipalities of Mertert and Oberbillig. This level of detail supplements the rounded figure published by the Luxembourg authorities. It is the initial budget presented for the project, not a final account of expenditure.
What the automation is intended to do
According to the technical explanations reported by Chronicle.lu, Aqua Pilot aims for conditional Level 3 automation. In practical terms, the system should be able to take charge of defined tasks, such as departure, the crossing of the Moselle and docking, while detecting obstacles under the specified conditions. The proposed system would therefore not leave the ferry to decide on its own when to set off.
The operator would remain responsible for authorising an automated crossing, monitoring its progress and intervening if necessary. Manual manoeuvres would remain possible. The stated aim is to automate routine operations, not to remove the crew. The report also specifies that the project has not yet reached the stage at which the system could manage dangerous situations autonomously.
This distinction matters in understanding the scope of the announcement. Here, “automated” means driving assistance for controlled tasks, with a person in charge on board, not a service without staff. The trials will, in particular, need to check that the equipment and software work under the actual conditions of the crossing.
Facilities to prepare before the trials
The timetable still depends on work and procedures. According to Chronicle.lu, contracts related to the automation technology and docking facilities have been delayed. Both landing stages must be ready before automated crossings can be tested. The delay could lead to an extension of the project under Interreg. The final cost could also slightly exceed the initial estimate, which was based on forecasts dating from 2023 and 2024.
The same report says that pilot trials could begin in 2028. The proposed sequence is gradual: checks of the equipment and software, followed by trials without passengers. People and vehicles would be allowed on board during automated crossings only after the system has been shown to work properly. The 2028 timeframe is therefore a prospect mentioned at the presentation, not a confirmed date for the service to enter operation for passengers.
For users, the ferry is still operated by its crew today. Aqua Pilot aims to prepare for a change in how it operates, but the announced stage concerns equipment, modifications and tests. Moving from these trials to automated transport available to the public will depend on how they go and on the operating conditions that are adopted.
References
- “Aqua Pilot”, an important step towards automated operation of the ferry between Germany and Luxembourg, Luxembourg government
- Luxembourg, Germany Target 2028 Trials for, Chronicle.lu
The Sankta Maria II leaves Oberbillig for the Luxembourg bank. Archive photo. Photo: Denise Hastert, Wikimedia Commons, CC BY-SA 4.0.