Miro G grounded in the Landes: who is stepping in to refloat it?

After the Miro G ran aground at Lit-et-Mixe, the shipowner must organise its refloating. The authorities are coordinating the response and monitoring risks to people and the environment.

Add LetzView to my preferred sources
A cargo ship seen from the Scottish coast
Image source and licence
Clément Proust, Pexels, Licence Pexels

The Miro G ran aground on the coast at Lit-et-Mixe, in the Landes, on 20 November. Four days later, an attempt to refloat it began, following preparations for a tow and operations to lighten the cargo ship. The shipowner must mobilise the necessary resources, while the public authorities coordinate the response and monitor risks to people and the environment. As of 24 November, the operation was under way, with no final outcome established in the information available.

From the first alert to running aground

CROSS-A Étel, the centre responsible for coordinating maritime rescue operations in its area, had been alerted towards the end of the day on Thursday 19 November. The cargo ship reported difficulties manoeuvring as wind and swell pushed it towards the coast. That evening, it dropped both anchor lines about 1.8 nautical miles, or nearly three kilometres, off Lit-et-Mixe. Gusts of up to 48 knots then caused it to drift towards the shore, where it ran aground early on Friday 20 November, according to the Atlantic Maritime Prefecture.

The captain requested the evacuation of the crew. A French Air and Space Force helicopter took part in the operation, while some of the sailors remained on board to facilitate the interventions to come. The information available reports no injuries among the crew.

The public response began even before the ship ran aground. The maritime prefect activated level 3 of the Atlantic maritime ORSEC emergency plan, which organises rescue operations at sea under his authority. The Biscay Plan, a French-Spanish maritime cooperation agreement, was also activated. Among other things, it enabled the Spanish tug Sar Gavia, which left Bilbao on 19 November, to be mobilised.

Responsibility remains with the shipowner

The mobilisation of state services does not mean that they are taking charge of refloating the vessel. On 20 November, the maritime prefect formally ordered the shipowner to take the necessary measures and mobilise the technical and human resources appropriate for refloating the vessel. The Maritime Prefecture explains that this responsibility must be exercised in conditions that protect people and the environment.

To prepare for the operation, the shipowner appointed Smit Salvage, a company specialising in marine salvage and refloating. Experts from Abeille International and specialists from the French Navy were also involved in the preparations, according to the Maritime Prefecture. Responsibility is therefore divided: the shipowner must mobilise the technical and human resources needed to refloat the vessel, while the authorities support and coordinate the response, ensuring safety and preventing pollution.

This distinction helps explain why a private operation is subject to close public oversight. A cargo ship grounded near the shore can require rescue services, expose teams to risks and threaten the marine environment. The state’s role is therefore not limited to authorising an attempt: it also involves organising the emergency response and monitoring collective risks.

Why wait for the right window?

Refloating the vessel depended on several conditions coming together. Deballasting involves removing some of the water held in the ballast tanks, the compartments that contribute to a vessel’s stability. The stated aim was to lighten the cargo ship to make it easier to free it from the sand and tow it away. The high tide was also expected to provide greater water depth. In its report on 24 November, franceinfo described the Abeille Bretagne in position to tow the Miro G, with the weather more favourable than in the preceding days.

The Abeille Bretagne was to remain at a distance from the shore. By midday, it was connected to the cargo ship by a 1,900-metre towline, according to AFP. The pull was first intended to turn the vessel towards the open sea. The maritime prefecture’s spokesperson warned that the hull could deform during this movement.

The Maritime Prefecture highlighted, in particular, the risk that the cargo ship could gradually become more deeply embedded if it remained where it was. Even if the vessel got free, a sandbank further offshore could complicate the next stage of the tow. These uncertainties explain the preparation time: a favourable tide alone was not enough to make the operation safe or feasible.

An attempt, not yet an outcome

In an update published after the attempt began, on 24 November, AFP reported that the cargo ship had pivoted from its original position. This movement did not establish that it had been refloated or that it could reach the open sea. The agency also reported that no pollution had then been detected by a surveillance aircraft, according to the Maritime Prefecture, and that preventive resources had been planned for both land and sea.

The distinction between preparation, the start of an operation and a successful refloating is essential. In the latest situation update dated 24 November among the information available, the operation had begun, but its outcome had not been established. Public monitoring focused both on the safety of the teams and on containing any possible pollution, while the shipowner remained responsible for mobilising the resources needed to refloat the vessel.