Submitting a connection request does not mean that a wind or solar farm can start feeding electricity into the grid. In the United States, the grid operator must first check whether the network can accommodate this generation at the proposed location and determine whether work is needed. This assessment, sometimes carried out alongside assessments of neighbouring projects, helps explain why a power plant can wait several years before it is commissioned.
A request triggers a study, not access to the grid
Large generation projects generally target substations connected to transmission lines: the high-voltage infrastructure that carries electricity over long distances. Before approving a connection, operators examine the effects of adding capacity to the local grid. The question is not simply whether the plant can generate electricity: they must also check that it can be transported without exceeding the capacity of the equipment involved.
This study can identify the need for upgrades. In its review of interconnection queues, Lawrence Berkeley National Laboratory describes an impact study that precedes connection and identifies work required, along with its potential costs. Until this assessment is complete and the connection conditions have been established, a request is therefore neither final approval nor a power plant under construction.
Neighbouring projects matter because they sometimes put demands on the same parts of the grid. Yale Climate Connections reports that operators may study several projects as a group rather than separately. This approach can provide a shared picture of requirements and works, but it also means that the assessment takes a set of requests and their combined effects into account. A project’s case is not limited to its own equipment.
A queue is not a list of power plants ready to go
Berkeley Lab’s figures show the scale of the gap between requested capacity and capacity actually connected. At the end of 2025, around 8 200 active generation projects were in the queues tracked by the study, representing 1 312 gigawatts (GW) of requested capacity. Storage accounted for an additional 749 GW. These figures relate to active requests, not installations that have already been built or are able to generate electricity.
The scope covers requests to connect generation to the transmission grid, submitted to operators covering around 98 % of installed capacity in the United States. Connections for consumers, those to the distribution grid and so-called ‘behind-the-meter’ installations are excluded. The results therefore do not describe every form of electricity connection in the country.
Another figure calls for careful interpretation: 549 GW had a connection agreement that had been drafted or signed but were not yet operational. An agreement marks a more advanced stage than a simple request, but does not mean the installation is already feeding electricity into the grid. The capacity concerned is still awaiting commissioning.
The composition of the queue also shows why its size cannot be equated with a construction programme. At the end of 2025, it included 773 GW of solar requests, 220 GW of wind and 253 GW of gas-fired power plants. These are requested capacities, within a total that also includes storage, not a forecast of future generation or a decision already made about which infrastructure will be built.
Long delays, but no universal timeframe
For projects actually built in 2025 in the regions for which data were available, the median time between the request and commissioning was more than five years. The median falls in the middle of the times observed in this group; it cannot be used to predict the schedule for a particular project. It cannot be used to predict the schedule for a particular project.
The statistic relates to completed installations, not all the requests still waiting in the queue. Projects that remain in the queue or leave it are not equivalent to those that go on to become operational. Of the capacity that requested a connection between 2000 and 2020, Berkeley Lab reports that 13 % was operational at the end of 2025, 75 % had been withdrawn and 10 % was still active. These proportions relate to this historical cohort, not to requests submitted in 2025.
Withdrawals help explain why queues change without the grid necessarily having connected more projects. Berkeley Lab’s review reports that more than 750 GW of requests were withdrawn in 2025 and that total active generation and storage requests stood at 2 061 GW at the end of the year, down 10 % from 2024 after peaking in 2023. The laboratory cites market conditions and procedural changes among the possible factors. The figures do not allow the withdrawals to be attributed to a single cause.
Faster assessment does not guarantee rapid commissioning
The options described by Yale Climate Connections include studying projects in groups and giving priority to areas with available transmission capacity. They are intended to ease a process in which queues are building up, but they do not remove the need to assess the effects of a connection and the work required. A faster study alone does not guarantee that a project will be built or that it can be commissioned by a particular date.
Yale Climate Connections also says that a federal bill, if passed, would require regulators to shorten the process. It is a proposal, not a rule already in force. Berkeley Lab also notes that it is too early to measure the full effects of the new interconnection rules.
The queue therefore measures pressure on the process of gaining access to the grid, not a reserve of power plants ready to generate. To understand a plant’s timeline, it is necessary to distinguish between its request, grid studies, any agreements, the work required and actual operation. Each of these stages addresses a different question.
References
- Transmission bottlenecks are holding up wind and solar projects, Yale Climate Connections.
- Queued Up 2026, Berkeley Lab.
- Backlog of power plants seeking transmission grid connection eased somewhat in 2025, Berkeley Lab.