Reuse in construction: how a material finds a second building site

From timber dismantled near Nantes to the reUSE platform presented by Esch in 2024, reuse depends on a precise chain: identify, dismantle, assess, store and find a new use.

Add LetzView to my preferred sources
Wooden pallets are stacked in front of a building under construction and scaffolding.
Image source and licence
Peter Dyllong, Pexels, Licence Pexels

Could a beam dismantled near Nantes have a second life in another building? Between dismantling, storage and finding a buyer, reuse requires a chain of operations, not just good intentions. Examples from Loire-Atlantique and Esch-sur-Alzette show the steps involved, and the differences between salvaging a material and actually putting it to use again.

First, distinguish between the different routes

Under the French framework, reuse means using a product or material again for the same purpose, provided it has not become waste. A partition that becomes a partition again is one example. Recycling, by contrast, transforms the material, by crushing or melting it down. Reuse in a different sense refers to returning a product that has become waste to use, possibly for a different purpose. These distinctions are those set out in the French framework presented by the French Building Federation; they shed light on the subject, but do not replace Luxembourg’s rules.

The word “salvage” is therefore not enough to establish that an item has been reused. It may have been dismantled and set aside without a new use having yet been found for it. For it to move from one building site to another, its condition must be preserved, its properties must be known, its transport must be organised and a project must be found for which it is suitable.

In Nantes, preserving components before moving them

In March 2026, an operation at the Salle Mimoun construction site in Grandchamp-des-Fontaines recovered structural timber. According to an account published by Articonnex, the company Douillard oversaw the dismantling and preparation on site. The reported total comprises 28,5 m³ of glued laminated timber beams and 9 m³ of solid-wood purlins, amounting to 37,5 m³ of timber and 18,8 tonnes of materials in total. Some beams measured up to 13,5 metres.

The dismantling method matters: the components were carefully taken apart, then cleared of metal fittings and other parts deemed undesirable before being stacked. The great lengths also required appropriate handling. A crane lorry transported the timber to Articonnex’s workshop and factory, where the company says the components are to be processed before being put back on the market.

This final step is important for understanding what the figure of 37,5 m³ measures, and what it does not. According to the company, it describes the volume of timber collected, not the amount already installed in a new structure. Salvaging preserves the potential for reuse; selling or processing a material does not, in itself, prove that it has found a place in a building.

Esch, an intermediary between supply and demand

In Esch-sur-Alzette, an initiative presented by the City in August 2024 illustrates another part of the chain: bringing people together. The reUSE project, initiated by Schroeder & Associés with BeFresh, was intended to facilitate exchanges between holders of materials from demolition projects and potential buyers. The inventory announced at the time covered materials from residential buildings on rue de la Fontaine, offered free of charge by the City. Interested parties had to register and reserve on a first come, first served basis; collection was planned on site in autumn 2024.

The municipal webpage also describes how the platform works in general: materials are listed in an inventory, after which buyers can submit an offer to the project owner, who selects a buyer. The minimum price is generally linked to the cost of demolition. The rue de la Fontaine case and the description of the process are information published in 2024; they do not allow us to conclude that these materials are still available today.

The platform tackles a practical obstacle. A salvaged item has an outlet only if someone knows it exists, can assess its characteristics and can incorporate it into a project. An inventory helps make the supply visible; it guarantees neither that an item is compatible with a particular building site nor that a transaction will be completed.

Identify and assess before deciding

Operations often begin before demolition. The French Building Federation notes that, in France, a survey of products, equipment, materials and waste (PEMD) is required before certain demolitions or major renovations. It is used to identify what is present and guide the management of the items. This French system should not automatically be transposed to Luxembourg.

Even when a product has been identified, putting it back into use depends on its condition and the requirements of the project receiving it. According to the FFB, traceability makes it possible to specify its origin, condition and destination. Assessment and responsibilities can also matter to companies and project owners. An announcement that a material is available therefore does not amount to general validation of its suitability for every use.

In Luxembourg, the Deconstruction Guide drawn up by the Luxembourg Institute of Science and Technology and the Environment Administration encourages public and private stakeholders to organise deconstruction in a structured and selective way. It gives priority to waste prevention, including reuse, ahead of recycling, recovery or disposal. It provides in particular for the sorting and collection of fractions such as wood, mineral materials, metal, glass and plaster. The guide also supports the trialling of a general technical clause on deconstruction and demolition; it is not proof that every building site is already applying these practices.

To track a material’s journey, several outcomes must therefore be considered separately: has the item been identified, dismantled without losing its integrity, described and assessed, stored in good conditions, and then offered for a new use? The final check is whether it has actually been put to that new use. Only then does the volume salvaged become a story of reuse, rather than a mere promise of a second life.

References

Illustrative photograph. Identifying and storing materials are two distinct stages in reuse. Photo: Peter Dyllong, Pexels, Pexels licence.